In order to gradually implement the Decree of the Moscow Government dated "On the placement of non-stationary retail facilities located in the city of Moscow on land plots, in buildings, structures, structures that are state-owned" and to bring legal acts of the Moscow Government into line with it, regulating certain issues of placement of objects of a small-scale retail network in the territory of the city of Moscow, decides: 1. To establish that: 1.1. Permits for placement of non-stationary objects of a small-scale retail network, issued in accordance with the established procedure in accordance with temporary schemes for the placement of non-stationary objects of a small-scale retail network for the first half of 2011: 1.1.1. For the objects specified in subparagraph 1 of paragraph 9 of Appendix 1 to the Decree of the Government of Moscow dated "On the placement of non-stationary retail facilities located in the city of Moscow on land plots, in buildings, structures, structures that are state-owned" - valid until November 1, 2011. 1.1.2. before determining the winner of an open auction for the right to conclude an agreement for the placement of a non-stationary retail facility in the specified location, but no later than September 30, 2011. 1.1.3. from the second half of 2011, - valid until September 30, 2011. 1.2 An economic entity that has a valid permit to locate a non-stationary retail facility for the sale of printed products in the place established by the scheme for locating non-stationary retail facilities has the right for reissuing such a permit for a contract for the placement of a non-stationary retail facility at the initial price of the auction for the right to conclude an agreement for the placement of a non-stationary retail facility. 2. Amend the Decree of the Government of Moscow dated "On the placement of non-stationary retail facilities located in the city of Moscow on land plots, in buildings, structures and structures that are state-owned" (as amended by the Decree of the Government of Moscow dated ) : 2.1. Paragraph one of paragraph 8 of Appendix 1 to the resolution after the words "one group" shall be supplemented with the words ", except for the activity for the sale of printed products. of goods (services) offered for sale out of their total amount is printed matter”. 2.2. In paragraph 7 of Appendix 2 to the Resolution, the words “within one percent to five percent of the initial price of the subject of the auction” shall be replaced by the words “by the organizer of the auction”. 2.3. Subparagraph 2 of paragraph 16 of Annex 2 to the Resolution shall be amended as follows: "2) an extract from the Unified State Register of Legal Entities (or a notarized copy of such an extract) - for legal entities, an extract from the Unified State Register of Individual Entrepreneurs ( or a notarized copy of such extract) - for individual entrepreneurs, issued no later than 6 months prior to the date of receipt of applications;". 3. Amend the Decree of the Government of Moscow dated "On the powers of the territorial executive bodies" (as amended by the Decrees of the Government of Moscow dated , dated): 3.1. Clause 2.6.5 of Appendix 1 to the resolution shall be stated as follows: "2.6.5. In accordance with the established procedure, it selects economic entities for organizing trade activities in the places determined by the scheme for the placement of non-stationary trade facilities, by holding an open auction, the subject of which is the right to conclude an agreement for the placement of a non-stationary trade facility; concludes an agreement for the placement of a non-stationary retail facility and issues a certificate of placement of a non-stationary retail facility. " as follows: “Submit proposals to the prefecture of the administrative district on the early termination of contracts for the placement of non-stationary retail facilities.” 5. Control over the implementation of this resolution shall be entrusted to the Deputy Mayor of Moscow in charge of economic policy Sharonov A.V.

GOVERNMENT OF THE RUSSIAN FEDERATION

RESOLUTION

ON APPROVAL OF THE LIST

ON THE PLANNING OF THE TERRITORY

In accordance with paragraph 5 of part 3 of article 41 Urban Planning Code Russian Federation The Government of the Russian Federation decides:

1. Approve the attached list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory.

Prime Minister

Russian Federation

D. MEDVEDEV

Approved

Government Decree

Russian Federation

SCROLL

CASES IN WHICH FOR CONSTRUCTION, RECONSTRUCTION

LINEAR OBJECT NO PREPARATION OF DOCUMENTATION IS REQUIRED

ON THE PLANNING OF THE TERRITORY

1. Construction, reconstruction of linear facilities that provide connection (technological connection) of facilities capital construction to existing electrical networks, networks of engineering and technical support (heat, gas, water supply, sanitation), provided that such connection (technological connection) of capital construction objects does not require the construction and (or) reconstruction of existing electrical networks, networks of engineering technical support and that such linear objects are:

a) power lines with a voltage class up to 35 kV inclusive, when the distance from the existing electrical networks to the boundaries of the site on which the connected power receiving devices are located is no more than 300 meters in cities and urban-type settlements and no more than 500 meters in countryside;

b) heating networks transporting water vapor with an operating pressure of up to 1.6 MPa inclusive or hot water with a temperature of up to 150 °C inclusive;

c) gas pipelines with a design working pressure of not more than 0.6 MPa, when the length from the existing gas supply networks to the connection point, measured in a straight line (the shortest distance), is not more than 500 meters in rural areas and not more than 300 meters within the boundaries of urban settlements ;

d) water pipes and conduits of all types with a diameter of up to 500 mm;

e) linear sewerage facilities with a diameter of up to 1000 mm.

2. Construction, reconstruction of an object that is part of an existing linear facility, provided that such construction, reconstruction is carried out in the right of way of the existing linear facility (in the security zone of the existing linear facility if the establishment of the right of way is not provided for by the legislation of the Russian Federation) and do not change the boundaries of zones with special conditions for the use of territories established in connection with the placement of an existing linear facility, and that the total area of ​​the said facility does not exceed 500 sq. meters, the height does not exceed 12 meters, the number of floors does not exceed 2 floors.

3. Construction, reconstruction of electrical networks, communication networks, networks of engineering and technical support (heat, gas, water supply, sanitation), which are located within one block, one microdistrict.

GOVERNMENT OF THE RUSSIAN FEDERATION

ON APPROVAL OF THE LIST

ON THE PLANNING OF THE TERRITORY

In accordance with clause 5 of part 3 of article 41 of the Town Planning Code of the Russian Federation, the Government of the Russian Federation decides:

1. Approve the attached list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory.

Prime Minister
Russian Federation
D. MEDVEDEV

Approved
Government Decree
Russian Federation
dated March 7, 2017 N 269

SCROLL
CASES IN WHICH FOR CONSTRUCTION, RECONSTRUCTION
LINEAR OBJECT NO PREPARATION OF DOCUMENTATION IS REQUIRED
ON THE PLANNING OF THE TERRITORY

1. Construction, reconstruction of linear facilities that provide connection (technological connection) of capital construction facilities to existing electrical networks, networks of engineering and technical support (heat, gas, water supply, sanitation), provided that such connection (technological connection) of facilities capital construction does not require the construction and (or) reconstruction of existing electrical networks, engineering and technical support networks, and that such linear objects are:

a) power lines with a voltage class up to 35 kV inclusive, when the distance from the existing electrical networks to the boundaries of the site where the connected power receiving devices are located is no more than 300 meters in cities and urban-type settlements and no more than 500 meters in rural areas;

b) heating networks transporting water vapor with an operating pressure of up to 1.6 MPa inclusive or hot water with a temperature of up to 150 °C inclusive;

c) gas pipelines with a design working pressure of not more than 0.6 MPa, when the length from the existing gas supply networks to the connection point, measured in a straight line (the shortest distance), is not more than 500 meters in rural areas and not more than 300 meters within the boundaries of urban settlements ;

d) water pipes and conduits of all types with a diameter of up to 500 mm;

e) linear sewerage facilities with a diameter of up to 1000 mm.

2. Construction, reconstruction of an object that is part of an existing linear facility, provided that such construction, reconstruction is carried out in the right of way of the existing linear facility (in the security zone of the existing linear facility if the establishment of the right of way is not provided for by the legislation of the Russian Federation) and do not change the boundaries of zones with special conditions for the use of territories established in connection with the placement of an existing linear facility, and that the total area of ​​the said facility does not exceed 500 sq. meters, the height does not exceed 12 meters, the number of floors does not exceed 2 floors.

3. Construction, reconstruction of electrical networks, communication networks, networks of engineering and technical support (heat, gas, water supply, sanitation), which are located within one block, one microdistrict.

On approval of the list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory

GOVERNMENT OF THE RUSSIAN FEDERATION DECISION dated March 7, 2017 No. 269 MOSCOW On approval of the list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory In accordance with clause 5 of part 3 of article 41 of the Town Planning Code of the Russian Federation stops: 1. Approve the attached list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory. 2. This Decree comes into force on July 1, 2017. Chairman of the Government of the Russian Federation D. Medvedev __________________________ APPROVED by Decree of the Government of the Russian Federation of March 7, 2017 No. 269 LIST of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for planning of the territory 1. Construction, reconstruction of linear facilities that provide connection (technological connection) of capital construction facilities to existing electrical networks, networks of engineering and technical support (heat, gas, water supply, sanitation), provided that such a connection (technological connection ) capital construction facilities do not require the construction and (or) reconstruction of existing electrical networks, engineering networks and that such linear facilities are: a) power lines with a voltage class of up to 35 kV inclusive, when the distance from the existing electrical networks to the boundaries of the site on which the connected power receiving devices are located is no more than 300 meters in cities and urban-type settlements and no more than 500 meters in rural areas; b) heating networks transporting water vapor with a working pressure of up to 1.6 MPa inclusive or hot water with a temperature of up to 150 ° C inclusive; c) gas pipelines with a design working pressure of not more than 0.6 MPa, when the length from the existing gas supply networks to the connection point, measured in a straight line (the shortest distance), is not more than 500 meters in rural areas and not more than 300 meters within the boundaries of urban settlements ; d) water pipes and conduits of all types with a diameter of up to 500 mm; e) linear sewerage facilities with a diameter of up to 1000 mm. 2. Construction, reconstruction of an object that is part of an existing linear facility, provided that such construction, reconstruction is carried out in the right of way of the existing linear facility (in the security zone of the existing linear facility if the establishment of the right of way is not provided for by the legislation of the Russian Federation) and do not change the boundaries of zones with special conditions for the use of territories established in connection with the placement of an existing linear facility, and that the total area of ​​the said facility does not exceed 500 sq. meters, the height does not exceed 12 meters, the number of floors does not exceed 2 floors. 3. Construction, reconstruction of electrical networks, communication networks, networks of engineering and technical support (heat, gas, water supply, sanitation), which are located within one block, one microdistrict. ___________

GOVERNMENT OF THE RUSSIAN FEDERATION

RESOLUTION

On approval of the list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory


In accordance with clause 5 of part 3 of article 41 of the Town Planning Code of the Russian Federation, the Government of the Russian Federation

decides:

1. Approve the attached list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory.

Prime Minister
Russian Federation
D. Medvedev

The list of cases in which the construction, reconstruction of a linear facility does not require the preparation of documentation for the planning of the territory

APPROVED
Government Decree
Russian Federation
dated March 7, 2017 N 269

1. Construction, reconstruction of linear facilities that provide connection (technological connection) of capital construction facilities to existing electrical networks, networks of engineering and technical support (heat, gas, water supply, sanitation), provided that such connection (technological connection) of facilities capital construction does not require the construction and (or) reconstruction of existing electrical networks, engineering and technical support networks, and that such linear objects are:

a) power lines with a voltage class up to 35 kV inclusive, when the distance from the existing electrical networks to the boundaries of the site where the connected power receiving devices are located is no more than 300 meters in cities and urban-type settlements and no more than 500 meters in rural areas;

b) heating networks transporting water vapor with a working pressure of up to 1.6 MPa inclusive or hot water with a temperature of up to 150 ° C inclusive;

c) gas pipelines with a design working pressure of not more than 0.6 MPa, when the length from the existing gas supply networks to the connection point, measured in a straight line (the shortest distance), is not more than 500 meters in rural areas and not more than 300 meters within the boundaries of urban settlements ;

d) water pipes and conduits of all types with a diameter of up to 500 mm;

e) linear sewerage facilities with a diameter of up to 1000 mm.

2. Construction, reconstruction of an object that is part of an existing linear facility, provided that such construction, reconstruction is carried out in the right of way of the existing linear facility (in the security zone of the existing linear facility if the establishment of the right of way is not provided for by the legislation of the Russian Federation) and do not change the boundaries of zones with special conditions for the use of territories established in connection with the placement of an existing linear facility, and that the total area of ​​the said facility does not exceed 500 sq. meters, the height does not exceed 12 meters, the number of floors does not exceed 2 floors.

3. Construction, reconstruction of electrical networks, communication networks, networks of engineering and technical support (heat, gas, water supply, sanitation), which are located within one block, one microdistrict.


Electronic text of the document